試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The inter-county connector highway had been in the proposed stage for decades. Neighborhoods have been concerned about ecological impacts, congestion, pollution and noise. In order to gain acceptance, certain community specifications need to be met. Finally, the community and local government have reached an agreement and the project is officially progressing. In order for the project to be successful, what must the project manager do?
A、Continuously solicit input from community stakeholders
B、Obtain legal representation incase specifications are not met
C、Communicate with community stakeholders regarding how the specifications are being met
D、Increase the budget since materials will be more costly