A project manager has been assigned to implement new server equipment into a data center. Through a risk workshop, the following two risks have been identified and assessed as highly likely to occur.1. Equipment is delayed due to shortages of key components.2. The customer has not initiated preparation of the data center, risking a delay in the project.What should the project manager do next?
A、Initiate the risk mitigation process
B、Conduct a Monte Carlo analysis
C、Add to the risk management plan
D、Initiate risk response planning