海贼王免费观看完整版在线全集1057,三国未删减完整版在线观看,成人在线免费高清视频,不卡成人,黄色的视频网站在线观看,亚洲综合图区,人人爽人人香蕉

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(4)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Three months into a project, the project manager learns that the project has a CPI of 1.1 and a SPI of 0.84. Three months later the CPI and SPI have changed to 0.9 and 1.0, respectively.In the three month interval, what course of action was likely taken by the project manager?
A、Reduced project scope
B、Authorized contingency plan
C、Increased resources
D、Reduced resources


相關(guān)試題

推薦文章