海贼王免费观看完整版在线全集1057,三国未删减完整版在线观看,成人在线免费高清视频,不卡成人,黄色的视频网站在线观看,亚洲综合图区,人人爽人人香蕉

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2013年上半年信息系統(tǒng)項目管理師培訓綜合知識考前模擬題
考試中心《2013年上半年信息系統(tǒng)項目管理師培訓綜合知識考前模擬題》在線考試
試卷年份2013年上半年
試題題型【單選題】
試題內容

The earned value technique is a commonly used method of performance measurement. It integrates project scope, schedule, and cost measures to help the project management team assess project performance. If a project's Cost Performance Index (CPI=EV/AC)  value less than 1.0, it means that ( )
A. the cost savings for work completed
B. the project is ahead of its planned schedule
C. the cost overrun for work completed
D. less work was completed than was planned


相關試題

推薦文章
合作網站內容